Arkisto: 'PlusVilla in Germany'

Day #210: Tiling Work Starts …

Keskiviikkona 21. huhtikuuta 2010 · Marius

hi. today alex started his tiling work. first it had been necessary to ground the floor and side, to protect house from any water damage. as you can see, i’m no longer allowed to enter my bathroom for the moment.

;-)

2010-04-21_foto-5.jpg2010-04-21_foto-6.jpg2010-04-21_foto-8.jpg

Day #208: Finalizing Sliding Doors

Keskiviikkona 21. huhtikuuta 2010 · Marius

moi, today we had some glass work which needed to be done. staff also finalized the lower area of the sliding doors with special bitumen tape.

2010-04-21_foto-9.jpg2010-04-21_foto-10.jpg

Day #206: Floor In Technic Room

Lauantaina 17. huhtikuuta 2010 · Marius

here we go with pics of todays work. the floor in the technic room has been finished. also the ceiling corner bars had been installed. also the area for the stone floor received some preparation work. last, the kitchen received it’s last wall panel to make the cabinets look flying.

2010-04-17_foto-7.jpg2010-04-17_foto-6.jpg2010-04-17_foto-5.jpg2010-04-17_foto-4.jpg

also our neighbour continued his house renovation. well… he promised us once again he won’t dismantle the whole house. ;-)

2010-04-17_foto-3.jpg

Day #202: Kitchen Finished

Lauantaina 17. huhtikuuta 2010 · Marius

moi, the kitchen has been finished. the BAX staff had been impressively fast in installing everything.

2010-04-17_foto-1.jpg2010-04-17_foto-2.jpg

Day #201: Kitchen Arrives

Maanantaina 12. huhtikuuta 2010 · Marius

terve. this morning the kitchen arrived safely. well… i’ve got to mention i didn’t had to travel far, as it’s coming from local company BAX. so far everything looks brilliant. i really liked the haptics of the object, as it feels really soft.

2010-04-12_foto.jpg2010-04-12_foto-1.jpg2010-04-12_foto-2.jpg2010-04-12_foto-3.jpg

Day #200: Floor In Smaller Room Finished

Sunnuntaina 11. huhtikuuta 2010 · Marius

terve. first of all apologies for having no pics of today’s work… but i simply forgot to take pics. the floor in one of the smaller rooms which i started yesterday has now been finished. what always sucks is installing the last boards: it is almost impossible to get them in as you can’t hammer as usual. i also cleaned the FERMACELL of spayed out glew. last, i prepared the area around the kitchen for scheduled kitchen setup.

Day #199: Floor Work & Electrics Finalization

Lauantaina 10. huhtikuuta 2010 · Marius

terve, i did some more square meters of the floor. as you can see, i’ve now also already started with one of the smaller rooms. during midday my electrician arrived surprisingly to finish most of his work. he did install the power for pressure drainage and also all switches and plugs. here the decision went for BUSCH & JÄGER future linear series. please note, we now also got our door bell.

2010-04-09_foto-9.jpg2010-04-09_foto-2.jpg2010-04-09_foto-5.jpg2010-04-09_foto-6.jpg2010-04-09_foto-7.jpg2010-04-09_foto-8.jpg

Day #198: Floor Work Continues

Lauantaina 10. huhtikuuta 2010 · Marius

this friday i did the floor beside the chimney.

2010-04-09_foto-1.jpg

Day #197: Floor Pavement In Bathroom Has Been Finished

Lauantaina 10. huhtikuuta 2010 · Marius

moi, the bathroom got its floor pavement. the decision went for FERMACELL 2 E 22, which has a height of 25 mm. please also note the socket for the bathtub.

2010-04-09_foto-10.jpg2010-04-09_foto.jpg

Day #194: Floor Work Continues …

Maanantaina 5. huhtikuuta 2010 · Marius

moi, today floor work continued. as you can see on pics (which had been made shortly before leaving the site) the chimney had been reached. the great wood quality makes it easy to install the floor panels. from time to time it’s difficult to finalize the areas with the last piece of panel as there is no chance to hammer them in. however, luckily we established some tricks how to achieve this with minor effort.

we also installed a wooden socket for the bath tube, so that the load transfer is 120% no problem.

2010-04-05_foto.jpg2010-04-05_foto-2.jpg2010-04-05_foto-1.jpg