Arkisto: 'PlusVilla in Germany'

Day #172: Floor Heating TBS System

Perjantaina 26. maaliskuuta 2010 · Marius

terve, here are a few more pics of the floor heating. as you can see, the floor plates are made of styropor. next heat-conducter plates are inserted. in those plates the special water tubes will be placed.

img_0691.jpg

power consumed on site had been disabled now. so activities on site had been simply placing the next used wood into the right logistic order.

Day #166: It’s Half To 1 O’Clock …

Sunnuntaina 7. maaliskuuta 2010 · Marius

… when this picture had been taken.

2010-03-07_foto.jpg

Day #165: Panels In Technic Room & Frame For Spark Protection

Lauantaina 6. maaliskuuta 2010 · Marius

terve, here we go with latest pictures. even though it might not be visibile on pics, progress is there. also winter came back to plusvilla for another weekend. we had once again 15 - 20 cm snow over night.

the technic room now features its panels within the wall. also the frame for the spark protection at the chimney had been installed. last but not least the installation wall in guest-toilet had been modified slightly.

what had been a real pain is making the area below the heating distribution unit dense regarding steam. finally i solved the problem today with the big hammer: steam shelter glew from a silicon gun. ;-)

2010-10-06_foto.jpg2010-10-06_foto-1.jpg2010-10-06_foto-2.jpg2010-10-06_foto-3.jpg

Day #163: Electrissity Work

Perjantaina 5. maaliskuuta 2010 · Marius

hi. electrissity work did continue. here you can see the first switched almost installed …

elefoto.jpgelefoto-1.jpg

Day #160: Roth Floor Heating

Tiistaina 2. maaliskuuta 2010 · Marius

moi, here you can see proceedings of today. the floor heating starts with isolation walls in which you place the styrofoam. next aluminium plates are installed, followed by the heating tubes. actually it’s pretty easy for our sanitary expert peter to install the system. if you like to find out more please visit manufacturer website at ClimaComfort TBS.

foto-16.jpgfoto-17.jpgfoto-18.jpg

Day #159: Bathroom Dry Walling

Tiistaina 2. maaliskuuta 2010 · Marius

terve, as you can see bathroom become more and more reality. here you can see the dry walling work which has been done today.

foto-13.jpgfoto-14.jpgfoto-15.jpg